Two internal emails discuss Project Alpha's timeline extension. Email 1 states: 'The delay is primarily due to scope creep resulting from frequent client change requests, which significantly expanded the project scope.' Email 2 states: 'Our current staffing levels were insufficient to meet the original aggressive deadline, regardless of client changes, indicating an initial underestimation of resource needs.' Based on both emails, what is the most likely underlying issue that contributed to the project delay?

A Poor communication between the project team and the client.
B Insufficient expertise within the project team.
C An unrealistic initial project deadline and resource allocation.
D Lack of commitment from the client to the original project plan.

✓ Correct Answer: Option C

Both scope creep (due to changes) and insufficient staffing (underestimation) point to issues with the initial planning, particularly setting an aggressive deadline and allocating resources. Thus, an unrealistic initial project deadline and resource allocation is the most likely underlying issue.

Related GMAT Exam Prep Questions