📊 GMAT Exam Prep

Two internal emails discuss Project Alpha's timeline extension. Email 1 states: 'The delay is primarily due to scope creep resulting from frequent client change requests, which significantly expanded the project scope.' Email 2 states: 'Our current staffing levels were insufficient to meet the original aggressive deadline, regardless of client changes, indicating an initial underestimation of resource needs.' Based on both emails, what is the most likely underlying issue that contributed to the project delay?

A Poor communication between the project team and the client.
B Insufficient expertise within the project team.
C An unrealistic initial project deadline and resource allocation.
D Lack of commitment from the client to the original project plan.

✓ Correct Answer: Option C

Both scope creep (due to changes) and insufficient staffing (underestimation) point to issues with the initial planning, particularly setting an aggressive deadline and allocating resources. Thus, an unrealistic initial project deadline and resource allocation is the most likely underlying issue.

💡 Why is C) the correct answer?

The correct answer to the question "Two internal emails discuss Project Alpha's timeline extension. Email 1 states: 'The delay is primarily due to scope creep resulting from frequent client change requests, which significantly expanded the project scope.' Email 2 states: 'Our current staffing levels were insufficient to meet the original aggressive deadline, regardless of client changes, indicating an initial underestimation of resource needs.' Based on both emails, what is the most likely underlying issue that contributed to the project delay?" is Option C: An unrealistic initial project deadline and resource allocation..

The other options — A) Poor communication between the project team and the client., B) Insufficient expertise within the project team., D) Lack of commitment from the client to the original project plan. — are incorrect for this GMAT Exam Prep question. As explained above: Both scope creep (due to changes) and insufficient staffing (underestimation) point to issues with the initial planning, particularly setting an aggressive deadline and allocating resources. Thus, an…

📚 About This GMAT Exam Prep Practice Question

This 3-level GMAT Exam Prep question from the Integrated Reasoning topic is part of BrainForge Quiz's free exam preparation library. Each question includes the correct answer and a detailed explanation to help you understand the underlying concept, not just memorize the answer.

How to use this page: Read the question above, consider all four options (A through D), then check the highlighted correct answer and explanation. For active timed practice, start a free GMAT Exam Prep practice test or use flashcards for spaced repetition review.

Related GMAT Exam Prep Questions