A project schedule table lists tasks, their durations, and dependencies. Task A (3 days) has no dependencies. Task B (5 days) depends on Task A. Task C (4 days) depends on Task A. Task D (6 days) depends on both Task B and Task C. Task E (2 days) depends on Task D. What is the minimum number of days to complete the entire project?
✓ Correct Answer: Option C
Path 1: A -> B -> D -> E = 3 + 5 + 6 + 2 = 16 days. Path 2: A -> C -> D -> E = 3 + 4 + 6 + 2 = 15 days. The critical path is the longest sequence, so 16 days.
📚 About This GMAT Exam Prep Practice Question
This 4-level GMAT Exam Prep question from the Integrated Reasoning topic is part of BrainForge Quiz's free exam preparation library. Each question includes the correct answer and a detailed explanation to help you understand the underlying concept, not just memorize the answer.
How to use this page: Read the question above, consider all four options (A through D), then check the highlighted correct answer and explanation. For active timed practice, start a free GMAT Exam Prep practice test or use flashcards for spaced repetition review.