A project management software displays a 'Task Dependency' matrix. Rows represent 'Predecessor Tasks' (A, B, C, D) and columns represent 'Successor Tasks' (W, X, Y, Z). An 'X' in a cell indicates that the row task must be completed before the column task can begin. If Task B has an 'X' in the column for Task Y, and Task Y has an 'X' in the column for Task Z, but Task B has no direct 'X' in the column for Task Z, what is the implied relationship between Task B and Task Z?
✓ Correct Answer: Option C
Task B must be completed before Task Y, and Task Y must be completed before Task Z. This establishes an indirect dependency where Task B must be completed before Task Z.
📚 About This GMAT Exam Prep Practice Question
This 3-level GMAT Exam Prep question from the Integrated Reasoning topic is part of BrainForge Quiz's free exam preparation library. Each question includes the correct answer and a detailed explanation to help you understand the underlying concept, not just memorize the answer.
How to use this page: Read the question above, consider all four options (A through D), then check the highlighted correct answer and explanation. For active timed practice, start a free GMAT Exam Prep practice test or use flashcards for spaced repetition review.