A company is considering five different software development projects. The table below lists their estimated costs, projected completion times, and associated risk levels. An internal policy dictates that no single project can have a 'High' risk level, and the total projected completion time for all selected projects must not exceed 24 months. If the company aims to maximize the number of projects undertaken, which of the following combinations of projects is feasible?
✓ Correct Answer: Option B
Assume Project data: (1: 8 months, Med Risk), (2: 6 months, Low Risk), (3: 9 months, Med Risk), (4: 7 months, High Risk), (5: 5 months, Low Risk). Option B (2, 3, 5) has no 'High' risk projects and a total time of 6+9+5 = 20 months, which is <= 24 months. Other options fail one or both criteria.