When forming a new team in an agile environment, the PM should first:

A Assign all tasks immediately
B Establish trust, define working agreements, and create a shared vision
C Create a detailed Gantt chart
D Write the project plan alone

✓ Correct Answer: Option B

Agile teams need psychological safety, shared purpose, and working agreements as a foundation.