When a team member underperforms, the PM should first:

A Terminate them immediately
B Have a private conversation to understand root causes and offer support
C Ignore the issue
D Report to senior management

✓ Correct Answer: Option B

Address underperformance privately, identify causes (training needs, personal issues), and develop an improvement plan.