📋 PMP Exam Prep

Three-point estimation uses:

A Only the most likely estimate
B Optimistic, most likely, and pessimistic estimates to calculate an expected value
C Only the pessimistic estimate
D Only the optimistic estimate

✓ Correct Answer: Option B

PERT: Expected = (Optimistic + 4×Most Likely + Pessimistic) / 6. Accounts for uncertainty.

💡 Why is B) the correct answer?

The correct answer to the question "Three-point estimation uses:" is Option B: Optimistic, most likely, and pessimistic estimates to calculate an expected value.

The other options — A) Only the most likely estimate, C) Only the pessimistic estimate, D) Only the optimistic estimate — are incorrect for this PMP Exam Prep question. As explained above: PERT: Expected = (Optimistic + 4×Most Likely + Pessimistic) / 6. Accounts for uncertainty.

📚 About This PMP Exam Prep Practice Question

This 2-level PMP Exam Prep question from the Process topic is part of BrainForge Quiz's free exam preparation library. Each question includes the correct answer and a detailed explanation to help you understand the underlying concept, not just memorize the answer.

How to use this page: Read the question above, consider all four options (A through D), then check the highlighted correct answer and explanation. For active timed practice, start a free PMP Exam Prep practice test or use flashcards for spaced repetition review.

Related PMP Exam Prep Questions