The critical path is:

A The shortest path through the network
B The longest path through the project schedule network, determining minimum duration
C The most expensive path
D The path with most resources

✓ Correct Answer: Option B

The critical path is the longest sequence of dependent activities — it determines the minimum project duration.

💡 Why is B) the correct answer?

The correct answer to the question "The critical path is:" is Option B: The longest path through the project schedule network, determining minimum duration.

The other options — A) The shortest path through the network, C) The most expensive path, D) The path with most resources — are incorrect for this PMP Exam Prep question. As explained above: The critical path is the longest sequence of dependent activities — it determines the minimum project duration.

📚 About This PMP Exam Prep Practice Question

This 2-level PMP Exam Prep question from the Process topic is part of BrainForge Quiz's free exam preparation library. Each question includes the correct answer and a detailed explanation to help you understand the underlying concept, not just memorize the answer.

How to use this page: Read the question above, consider all four options (A through D), then check the highlighted correct answer and explanation. For active timed practice, start a free PMP Exam Prep practice test or use flashcards for spaced repetition review.

Related PMP Exam Prep Questions