The critical path in a project schedule is:

A The shortest path
B The longest sequence of dependent activities that determines the minimum project duration
C The cheapest path
D Any random path

✓ Correct Answer: Option B

Critical path: longest duration path through the network. Any delay on critical path activities delays the entire project.