📋 PMP Exam Prep

The critical path in a project schedule is:

A The shortest path
B The longest sequence of dependent activities that determines the minimum project duration
C The cheapest path
D Any random path

✓ Correct Answer: Option B

Critical path: longest duration path through the network. Any delay on critical path activities delays the entire project.

💡 Why is B) the correct answer?

The correct answer to the question "The critical path in a project schedule is:" is Option B: The longest sequence of dependent activities that determines the minimum project duration.

The other options — A) The shortest path, C) The cheapest path, D) Any random path — are incorrect for this PMP Exam Prep question. As explained above: Critical path: longest duration path through the network. Any delay on critical path activities delays the entire project.

📚 About This PMP Exam Prep Practice Question

This 2-level PMP Exam Prep question from the Process topic is part of BrainForge Quiz's free exam preparation library. Each question includes the correct answer and a detailed explanation to help you understand the underlying concept, not just memorize the answer.

How to use this page: Read the question above, consider all four options (A through D), then check the highlighted correct answer and explanation. For active timed practice, start a free PMP Exam Prep practice test or use flashcards for spaced repetition review.

Related PMP Exam Prep Questions