📋 PMP Exam Prep

Strategic alignment means the project:

A Ignores company strategy
B Supports and contributes to the organizations strategic goals and objectives
C Focuses only on cost
D Is independent of organizational goals

✓ Correct Answer: Option B

Projects should be aligned with and contribute to the organizations strategic objectives.