๐Ÿ“‹ PMP Exam Prep

SPI (Schedule Performance Index) > 1.0 means the project is:

A Behind schedule
B Ahead of schedule
C On schedule exactly
D Over budget

โœ“ Correct Answer: Option B

SPI = EV/PV. SPI > 1.0 means more work has been accomplished than planned โ€” ahead of schedule.

๐Ÿ’ก Why is B) the correct answer?

The correct answer to the question "SPI (Schedule Performance Index) > 1.0 means the project is:" is Option B: Ahead of schedule.

The other options โ€” A) Behind schedule, C) On schedule exactly, D) Over budget โ€” are incorrect for this PMP Exam Prep question. As explained above: SPI = EV/PV. SPI > 1.0 means more work has been accomplished than planned โ€” ahead of schedule.

๐Ÿ“š About This PMP Exam Prep Practice Question

This 2-level PMP Exam Prep question from the Process topic is part of BrainForge Quiz's free exam preparation library. Each question includes the correct answer and a detailed explanation to help you understand the underlying concept, not just memorize the answer.

How to use this page: Read the question above, consider all four options (A through D), then check the highlighted correct answer and explanation. For active timed practice, start a free PMP Exam Prep practice test or use flashcards for spaced repetition review.

Related PMP Exam Prep Questions