Schedule compression can use crashing which involves:

A Reducing scope
B Adding resources to critical path activities to shorten their duration (at additional cost)
C Extending deadlines
D Removing activities

✓ Correct Answer: Option B

Crashing: add resources to shorten critical path tasks. Cost increases but duration decreases. Only crash critical path activities.