📋 PMP Exam Prep

Resource leveling may result in:

A Shorter project duration
B Extended project duration to resolve resource over-allocation
C More resources
D Lower quality

✓ Correct Answer: Option B

Resource leveling adjusts the schedule to eliminate over-allocation, often extending the project timeline.

💡 Why is B) the correct answer?

The correct answer to the question "Resource leveling may result in:" is Option B: Extended project duration to resolve resource over-allocation.

The other options — A) Shorter project duration, C) More resources, D) Lower quality — are incorrect for this PMP Exam Prep question. As explained above: Resource leveling adjusts the schedule to eliminate over-allocation, often extending the project timeline.

📚 About This PMP Exam Prep Practice Question

This 2-level PMP Exam Prep question from the People topic is part of BrainForge Quiz's free exam preparation library. Each question includes the correct answer and a detailed explanation to help you understand the underlying concept, not just memorize the answer.

How to use this page: Read the question above, consider all four options (A through D), then check the highlighted correct answer and explanation. For active timed practice, start a free PMP Exam Prep practice test or use flashcards for spaced repetition review.

Related PMP Exam Prep Questions