Portfolio management differs from project management in that it:

A Manages a single project
B Selects, prioritizes, and governs a collection of projects and programs to achieve strategic objectives
C Focuses on daily tasks
D Ignores strategy

✓ Correct Answer: Option B

Portfolio management: strategic selection and prioritization of projects/programs. Maximizes organizational value within resource constraints.