Portfolio management differs from project management in that it:

A Manages a single project
B Selects, prioritizes, and governs a collection of projects and programs to achieve strategic objectives
C Focuses on daily tasks
D Ignores strategy

✓ Correct Answer: Option B

Portfolio management: strategic selection and prioritization of projects/programs. Maximizes organizational value within resource constraints.

💡 Why is B) the correct answer?

The correct answer to the question "Portfolio management differs from project management in that it:" is Option B: Selects, prioritizes, and governs a collection of projects and programs to achieve strategic objectives.

The other options — A) Manages a single project, C) Focuses on daily tasks, D) Ignores strategy — are incorrect for this PMP Exam Prep question. As explained above: Portfolio management: strategic selection and prioritization of projects/programs. Maximizes organizational value within resource constraints.

📚 About This PMP Exam Prep Practice Question

This 2-level PMP Exam Prep question from the Business Environment topic is part of BrainForge Quiz's free exam preparation library. Each question includes the correct answer and a detailed explanation to help you understand the underlying concept, not just memorize the answer.

How to use this page: Read the question above, consider all four options (A through D), then check the highlighted correct answer and explanation. For active timed practice, start a free PMP Exam Prep practice test or use flashcards for spaced repetition review.

Related PMP Exam Prep Questions