Liquidated damages clauses are enforceable if:

A They are any amount chosen by the parties
B The amount is reasonable in relation to anticipated or actual loss and damages were difficult to estimate
C They exceed actual damages
D Both parties are merchants

✓ Correct Answer: Option B

Liquidated damages must be a reasonable estimate of anticipated loss at time of contracting, and actual damages must be difficult to determine. Otherwise, it is an unenforceable penalty.