📋 PMP Exam Prep

In stakeholder engagement, the strategy for "high power, high interest" stakeholders is:

A Monitor
B Manage closely with active engagement
C Keep informed
D Keep satisfied

✓ Correct Answer: Option B

High power + high interest stakeholders need close management with proactive, frequent engagement.