📋 PMP Exam Prep

In Monte Carlo simulation for project scheduling:

A A single estimate is used
B Multiple iterations model probability distributions of possible schedule outcomes
C Only the critical path is analyzed
D Resources are ignored

✓ Correct Answer: Option B

Monte Carlo runs thousands of iterations with probability distributions to model likely project duration ranges.

💡 Why is B) the correct answer?

The correct answer to the question "In Monte Carlo simulation for project scheduling:" is Option B: Multiple iterations model probability distributions of possible schedule outcomes.

The other options — A) A single estimate is used, C) Only the critical path is analyzed, D) Resources are ignored — are incorrect for this PMP Exam Prep question. As explained above: Monte Carlo runs thousands of iterations with probability distributions to model likely project duration ranges.

📚 About This PMP Exam Prep Practice Question

This 3-level PMP Exam Prep question from the Process topic is part of BrainForge Quiz's free exam preparation library. Each question includes the correct answer and a detailed explanation to help you understand the underlying concept, not just memorize the answer.

How to use this page: Read the question above, consider all four options (A through D), then check the highlighted correct answer and explanation. For active timed practice, start a free PMP Exam Prep practice test or use flashcards for spaced repetition review.

Related PMP Exam Prep Questions