In agile, a product backlog is:

A A bug list
B A prioritized list of features, stories, and requirements maintained by the product owner
C A completed work list
D A team roster

✓ Correct Answer: Option B

Product backlog: dynamic, ordered list of everything needed in the product. Product Owner prioritizes by value.

💡 Why is B) the correct answer?

The correct answer to the question "In agile, a product backlog is:" is Option B: A prioritized list of features, stories, and requirements maintained by the product owner.

The other options — A) A bug list, C) A completed work list, D) A team roster — are incorrect for this PMP Exam Prep question. As explained above: Product backlog: dynamic, ordered list of everything needed in the product. Product Owner prioritizes by value.

📚 About This PMP Exam Prep Practice Question

This 1-level PMP Exam Prep question from the Process topic is part of BrainForge Quiz's free exam preparation library. Each question includes the correct answer and a detailed explanation to help you understand the underlying concept, not just memorize the answer.

How to use this page: Read the question above, consider all four options (A through D), then check the highlighted correct answer and explanation. For active timed practice, start a free PMP Exam Prep practice test or use flashcards for spaced repetition review.

Related PMP Exam Prep Questions