In a projectized organization, the PM has:

A No authority
B High to full authority over the project team and resources
C Only advisory authority
D Less authority than a functional manager

โœ“ Correct Answer: Option B

In projectized organizations, PMs have significant authority; team members are dedicated to the project.

๐Ÿ’ก Why is B) the correct answer?

The correct answer to the question "In a projectized organization, the PM has:" is Option B: High to full authority over the project team and resources.

The other options โ€” A) No authority, C) Only advisory authority, D) Less authority than a functional manager โ€” are incorrect for this PMP Exam Prep question. As explained above: In projectized organizations, PMs have significant authority; team members are dedicated to the project.

๐Ÿ“š About This PMP Exam Prep Practice Question

This 2-level PMP Exam Prep question from the Business Environment topic is part of BrainForge Quiz's free exam preparation library. Each question includes the correct answer and a detailed explanation to help you understand the underlying concept, not just memorize the answer.

How to use this page: Read the question above, consider all four options (A through D), then check the highlighted correct answer and explanation. For active timed practice, start a free PMP Exam Prep practice test or use flashcards for spaced repetition review.