In a functional organization, project managers typically have:

A Full authority
B Little or no formal authority; functional managers control resources
C More authority than executives
D Complete budget control

✓ Correct Answer: Option B

In functional organizations, functional managers hold authority; PMs may act as coordinators with limited power.