In a functional organization, project managers typically have:

A Full authority
B Little or no formal authority; functional managers control resources
C More authority than executives
D Complete budget control

✓ Correct Answer: Option B

In functional organizations, functional managers hold authority; PMs may act as coordinators with limited power.

💡 Why is B) the correct answer?

The correct answer to the question "In a functional organization, project managers typically have:" is Option B: Little or no formal authority; functional managers control resources.

The other options — A) Full authority, C) More authority than executives, D) Complete budget control — are incorrect for this PMP Exam Prep question. As explained above: In functional organizations, functional managers hold authority; PMs may act as coordinators with limited power.

📚 About This PMP Exam Prep Practice Question

This 2-level PMP Exam Prep question from the Business Environment topic is part of BrainForge Quiz's free exam preparation library. Each question includes the correct answer and a detailed explanation to help you understand the underlying concept, not just memorize the answer.

How to use this page: Read the question above, consider all four options (A through D), then check the highlighted correct answer and explanation. For active timed practice, start a free PMP Exam Prep practice test or use flashcards for spaced repetition review.

Related PMP Exam Prep Questions