๐Ÿ“‹ PMP Exam Prep

Estimating using analogous estimation relies on:

A Detailed bottom-up analysis
B Historical data from similar past projects
C Expert opinions only
D Mathematical models

โœ“ Correct Answer: Option B

Analogous estimation uses actual data from similar past projects as a basis for estimating the current project.

๐Ÿ’ก Why is B) the correct answer?

The correct answer to the question "Estimating using analogous estimation relies on:" is Option B: Historical data from similar past projects.

The other options โ€” A) Detailed bottom-up analysis, C) Expert opinions only, D) Mathematical models โ€” are incorrect for this PMP Exam Prep question. As explained above: Analogous estimation uses actual data from similar past projects as a basis for estimating the current project.

๐Ÿ“š About This PMP Exam Prep Practice Question

This 2-level PMP Exam Prep question from the Process topic is part of BrainForge Quiz's free exam preparation library. Each question includes the correct answer and a detailed explanation to help you understand the underlying concept, not just memorize the answer.

How to use this page: Read the question above, consider all four options (A through D), then check the highlighted correct answer and explanation. For active timed practice, start a free PMP Exam Prep practice test or use flashcards for spaced repetition review.

Related PMP Exam Prep Questions