Earned Value Management (EVM) uses which three key metrics?
โ Correct Answer: Option B
EVM: PV (budgeted work scheduled), EV (budgeted cost of work performed), AC (actual cost spent). CPI = EV/AC, SPI = EV/PV.
๐ About This PMP Exam Prep Practice Question
This 2-level PMP Exam Prep question from the Process topic is part of BrainForge Quiz's free exam preparation library. Each question includes the correct answer and a detailed explanation to help you understand the underlying concept, not just memorize the answer.
How to use this page: Read the question above, consider all four options (A through D), then check the highlighted correct answer and explanation. For active timed practice, start a free PMP Exam Prep practice test or use flashcards for spaced repetition review.