Earned Value Management (EVM) integrates:

A Only cost data
B Scope, schedule, and cost performance measurement
C Only schedule data
D Only quality metrics

โœ“ Correct Answer: Option B

EVM combines scope (work done), schedule (timing), and cost (spending) into an integrated measurement system.

๐Ÿ’ก Why is B) the correct answer?

The correct answer to the question "Earned Value Management (EVM) integrates:" is Option B: Scope, schedule, and cost performance measurement.

The other options โ€” A) Only cost data, C) Only schedule data, D) Only quality metrics โ€” are incorrect for this PMP Exam Prep question. As explained above: EVM combines scope (work done), schedule (timing), and cost (spending) into an integrated measurement system.

๐Ÿ“š About This PMP Exam Prep Practice Question

This 2-level PMP Exam Prep question from the Process topic is part of BrainForge Quiz's free exam preparation library. Each question includes the correct answer and a detailed explanation to help you understand the underlying concept, not just memorize the answer.

How to use this page: Read the question above, consider all four options (A through D), then check the highlighted correct answer and explanation. For active timed practice, start a free PMP Exam Prep practice test or use flashcards for spaced repetition review.

Related PMP Exam Prep Questions