During the storming phase of team development, a PM should:

A Ignore conflicts
B Facilitate constructive conflict resolution and help establish ground rules
C Dissolve the team
D Assign blame

✓ Correct Answer: Option B

Storming is natural; PM facilitates healthy conflict resolution, establishes norms, and helps the team move to norming.

💡 Why is B) the correct answer?

The correct answer to the question "During the storming phase of team development, a PM should:" is Option B: Facilitate constructive conflict resolution and help establish ground rules.

The other options — A) Ignore conflicts, C) Dissolve the team, D) Assign blame — are incorrect for this PMP Exam Prep question. As explained above: Storming is natural; PM facilitates healthy conflict resolution, establishes norms, and helps the team move to norming.

📚 About This PMP Exam Prep Practice Question

This 2-level PMP Exam Prep question from the People topic is part of BrainForge Quiz's free exam preparation library. Each question includes the correct answer and a detailed explanation to help you understand the underlying concept, not just memorize the answer.

How to use this page: Read the question above, consider all four options (A through D), then check the highlighted correct answer and explanation. For active timed practice, start a free PMP Exam Prep practice test or use flashcards for spaced repetition review.

Related PMP Exam Prep Questions