Crashing a project schedule means:

A Letting it fail
B Adding resources to critical path activities to reduce duration at increased cost
C Removing activities
D Extending the deadline

✓ Correct Answer: Option B

Crashing adds resources (or overtime) to critical path activities to shorten duration — typically increases cost.