Consequential damages in contract are recoverable when:
✓ Correct Answer: Option B
Hadley v. Baxendale: consequential damages (special or indirect losses) are recoverable only if foreseeable at the time of contracting — either arising naturally or from special circumstances communicated to the breaching party.