A Work Breakdown Structure (WBS) is:

A A risk register
B A hierarchical decomposition of total project scope into manageable work packages
C A schedule
D A budget document

✓ Correct Answer: Option B

The WBS decomposes the project into progressively smaller, manageable deliverables and work packages.