📋 PMP Exam Prep

A Work Breakdown Structure (WBS) decomposes:

A Team roles
B Project scope into smaller, manageable deliverable-oriented components
C The budget only
D The schedule only

✓ Correct Answer: Option B

WBS: hierarchical decomposition of total scope into work packages. 100% rule—all work must be captured.

💡 Why is B) the correct answer?

The correct answer to the question "A Work Breakdown Structure (WBS) decomposes:" is Option B: Project scope into smaller, manageable deliverable-oriented components.

The other options — A) Team roles, C) The budget only, D) The schedule only — are incorrect for this PMP Exam Prep question. As explained above: WBS: hierarchical decomposition of total scope into work packages. 100% rule—all work must be captured.

📚 About This PMP Exam Prep Practice Question

This 2-level PMP Exam Prep question from the Process topic is part of BrainForge Quiz's free exam preparation library. Each question includes the correct answer and a detailed explanation to help you understand the underlying concept, not just memorize the answer.

How to use this page: Read the question above, consider all four options (A through D), then check the highlighted correct answer and explanation. For active timed practice, start a free PMP Exam Prep practice test or use flashcards for spaced repetition review.

Related PMP Exam Prep Questions