๐Ÿ“‹ PMP Exam Prep

A RAID log tracks:

A Project schedule only
B Risks, Assumptions, Issues, and Dependencies
C Only defects
D Only team attendance

โœ“ Correct Answer: Option B

RAID: Risks, Assumptions, Issues, Dependencies โ€” a comprehensive tracking tool for project concerns.

๐Ÿ’ก Why is B) the correct answer?

The correct answer to the question "A RAID log tracks:" is Option B: Risks, Assumptions, Issues, and Dependencies.

The other options โ€” A) Project schedule only, C) Only defects, D) Only team attendance โ€” are incorrect for this PMP Exam Prep question. As explained above: RAID: Risks, Assumptions, Issues, Dependencies โ€” a comprehensive tracking tool for project concerns.

๐Ÿ“š About This PMP Exam Prep Practice Question

This 2-level PMP Exam Prep question from the Process topic is part of BrainForge Quiz's free exam preparation library. Each question includes the correct answer and a detailed explanation to help you understand the underlying concept, not just memorize the answer.

How to use this page: Read the question above, consider all four options (A through D), then check the highlighted correct answer and explanation. For active timed practice, start a free PMP Exam Prep practice test or use flashcards for spaced repetition review.

Related PMP Exam Prep Questions