A project charter formally:

A Closes the project
B Authorizes the project and gives the PM authority to apply resources
C Replaces the project plan
D Lists all tasks

✓ Correct Answer: Option B

The project charter formally authorizes the project, defines high-level requirements, and empowers the PM.