A project business case justifies the project by:

A Listing team members
B Documenting the business need, expected benefits, and financial analysis
C Defining the schedule only
D Assigning resources

✓ Correct Answer: Option B

The business case provides the rationale for initiating the project with expected benefits and ROI.