A Kanban board visualizes:

A Only completed work
B Work items flowing through stages (e.g., To Do, In Progress, Done) with WIP limits
C Only planned work
D Team availability

✓ Correct Answer: Option B

Kanban: visual workflow management with columns for states, WIP limits to prevent overload, pull-based system.

💡 Why is B) the correct answer?

The correct answer to the question "A Kanban board visualizes:" is Option B: Work items flowing through stages (e.g., To Do, In Progress, Done) with WIP limits.

The other options — A) Only completed work, C) Only planned work, D) Team availability — are incorrect for this PMP Exam Prep question. As explained above: Kanban: visual workflow management with columns for states, WIP limits to prevent overload, pull-based system.

📚 About This PMP Exam Prep Practice Question

This 1-level PMP Exam Prep question from the Process topic is part of BrainForge Quiz's free exam preparation library. Each question includes the correct answer and a detailed explanation to help you understand the underlying concept, not just memorize the answer.

How to use this page: Read the question above, consider all four options (A through D), then check the highlighted correct answer and explanation. For active timed practice, start a free PMP Exam Prep practice test or use flashcards for spaced repetition review.

Related PMP Exam Prep Questions