📋 PMP Exam Prep

A Kanban board visualizes:

A Only completed work
B Work items flowing through stages (e.g., To Do, In Progress, Done) with WIP limits
C Only planned work
D Team availability

✓ Correct Answer: Option B

Kanban: visual workflow management with columns for states, WIP limits to prevent overload, pull-based system.