A feasibility study evaluates:

A Only the project schedule
B Whether a project is technically, economically, and operationally viable
C Only the budget
D Only the team structure

✓ Correct Answer: Option B

Feasibility studies assess technical, economic, legal, operational, and scheduling viability before committing resources.

💡 Why is B) the correct answer?

The correct answer to the question "A feasibility study evaluates:" is Option B: Whether a project is technically, economically, and operationally viable.

The other options — A) Only the project schedule, C) Only the budget, D) Only the team structure — are incorrect for this PMP Exam Prep question. As explained above: Feasibility studies assess technical, economic, legal, operational, and scheduling viability before committing resources.

📚 About This PMP Exam Prep Practice Question

This 1-level PMP Exam Prep question from the Business Environment topic is part of BrainForge Quiz's free exam preparation library. Each question includes the correct answer and a detailed explanation to help you understand the underlying concept, not just memorize the answer.

How to use this page: Read the question above, consider all four options (A through D), then check the highlighted correct answer and explanation. For active timed practice, start a free PMP Exam Prep practice test or use flashcards for spaced repetition review.

Related PMP Exam Prep Questions