A change control board (CCB) is responsible for:

A Making all project decisions
B Reviewing, evaluating, and approving or rejecting change requests
C Writing the project plan
D Managing daily tasks

✓ Correct Answer: Option B

The CCB reviews proposed changes, assesses their impact, and makes formal approve/reject decisions.