A burnup chart shows:

A Remaining work only
B Cumulative work completed versus total scope, making scope changes visible
C Team velocity only
D Cost variance

✓ Correct Answer: Option B

Burnup charts show completed work and total scope lines, making it easy to see scope changes and progress.

💡 Why is B) the correct answer?

The correct answer to the question "A burnup chart shows:" is Option B: Cumulative work completed versus total scope, making scope changes visible.

The other options — A) Remaining work only, C) Team velocity only, D) Cost variance — are incorrect for this PMP Exam Prep question. As explained above: Burnup charts show completed work and total scope lines, making it easy to see scope changes and progress.

📚 About This PMP Exam Prep Practice Question

This 2-level PMP Exam Prep question from the Business Environment topic is part of BrainForge Quiz's free exam preparation library. Each question includes the correct answer and a detailed explanation to help you understand the underlying concept, not just memorize the answer.

How to use this page: Read the question above, consider all four options (A through D), then check the highlighted correct answer and explanation. For active timed practice, start a free PMP Exam Prep practice test or use flashcards for spaced repetition review.

Related PMP Exam Prep Questions