📋 PMP Exam Prep

A burnup chart shows:

A Remaining work only
B Cumulative work completed versus total scope, making scope changes visible
C Team velocity only
D Cost variance

✓ Correct Answer: Option B

Burnup charts show completed work and total scope lines, making it easy to see scope changes and progress.

Related PMP Exam Prep Questions