A burndown chart in Agile shows:

A Total project cost
B The amount of work remaining versus time in a sprint
C Team headcount
D Stakeholder engagement

✓ Correct Answer: Option B

Burndown charts track remaining work (story points or tasks) against time to forecast sprint completion.