A benefit-cost ratio (BCR) greater than 1.0 indicates:

A The project should be rejected
B Expected benefits exceed expected costs — the project is financially justified
C Costs exceed benefits
D The project breaks even

✓ Correct Answer: Option B

BCR > 1.0 means benefits outweigh costs. Higher BCR = more financially attractive project.